SHUMEN WATER CYCLE IMPROVEMENTS IN BULGARIA, ISPA MEASURE – EUROPAID/120223/D/SV/BG  TECHNICAL ASSISTANCE FOR WATER CYCLE SURVEY, DETAILED DESIGN, PREPARATION of WORK TENDER DOSSIER FOR CONSTRUCTION AND SUPERVISION OF THE CONSTRUCTION WORKS FOR SHUMEN WATER PROJECT

Employer/ Beneficiary: Consortium DIWI-IGIP-LOPP/ Municipality of Shumen Implementation period: 11/2007 – 01/2009 Design parameters: Water supply network – 61 km; Sewerage network – 22 km; Main water supply pipeline –…

INTEGRATED WATER CYCLE, POMORIE, BURGAS REGION   SITE 1: POMORIE WASTE WATER TREATMENT PLANT (WWTP) RECONSTRUCTION AND MODERNISATION  SITE 2: POMORIE WATER SUPPLY AND SEWERAGE NETWORK RECONSTRUCTION AND REHABILITATION

Employer/ Beneficiary: Municipality of Pomorie Implementation period: 03/2012 – 08/2012 Design parameters: WWTP capacity of 56 626 PE (peak season) and 21 867 PE (off-peak season), with nitrogen and phosphorus…

TECHNICAL ASSISTANCE FOR PREPARATION FOR RECONSTRUCTION AND COMPLETION OF WATER DISTRIBUTION AND SEWERAGE NETWORKS, POTABLE WATER TREATMENT PLANT AND WASTE WATER TREATMENT PLANT OF TOWN OF SIMITLI, MUNICIPALITY OF SIMITLI

Employer/ Beneficiary: Municipality of Simitli Implementation period: 04/2009 – 03/2010 Design parameters: Internal water supply network – 22,7 km; Internal Sewerage network – 28,3 km; Internal separate sewer network –…

TECHNICAL ASSISTANCE FOR PREPARATION FOR RECONSTRUCTION AND COMPLETION OF WATER DISTRIBUTION AND SEWERAGE NETWORKS, POTABLE WATER TREATMENT PLANT AND WASTE WATER TREATMENT PLANT OF VILLAGE OF KRUPNIK, MUNICIPALITY OF SIMITLI

Employer/ Beneficiary: Municipality of Simitli Implementation period: 04/2009 – 03/2010 Design parameters: Internal water supply network – 17,2 km; Water supply household connections – 6,7 km; Internal separate sewer network…