TECHNICAL ASSISTANCE FOR PREPARATION FOR RECONSTRUCTION AND COMPLETION OF WATER DISTRIBUTION AND SEWERAGE NETWORKS, POTABLE WATER TREATMENT PLANT AND WASTE WATER TREATMENT PLANT OF TOWN OF SIMITLI, MUNICIPALITY OF SIMITLI

By 0
430
TECHNICAL ASSISTANCE FOR PREPARATION FOR RECONSTRUCTION AND COMPLETION OF WATER DISTRIBUTION AND SEWERAGE NETWORKS, POTABLE WATER TREATMENT PLANT AND WASTE WATER TREATMENT PLANT OF TOWN OF SIMITLI, MUNICIPALITY OF SIMITLI

Employer/ Beneficiary: Municipality of Simitli

Implementation period: 04/2009 – 03/2010

Design parameters:

  • Internal water supply network – 22,7 km;
  • Internal Sewerage network – 28,3 km;
  • Internal separate sewer network – 26,6 km;
  • PWTP with capacity of:
    – Q = 44 l/s;
  • 2 pcs. SPS with capacity of:
    – Q = 30 l/s;
    – Q = 20 l/s.
  • WWTP with capacity of:
    – 10 960 PE;
    – Q = 1 874 m³/d;
    – Supplying sewage collector – 415 m;
    – Pressure collector – 1250 m;
    – Common gravity collector – 1490 m;

Performed activities:

  • Preparation of feasibility study (FS);
  • Preliminary design – 2 options, options analysis;
  • Cost estimates, incl. determination of operating costs and cost of 1 m³ of treated water;
  • Detailed design in all design parts;
  • Coordination and approval of the project with all responsible institutions to obtain necessary permits.

Investment value of the project: 5 650 800 € (without VAT)