ENGINEERING - DESIGN, DESIGN SUPERVISION AND EXECUTION OF CONSTRUCTION AND ASSEMBLY WORK RELATED TO THE PROJECT “DEMONSTRATION CENTER FOR LOCAL INSTALLATIONS (WWTP’S) AND TECHNOLOGIES FOR WASTE WATER TREATMENT”

Employer/ Beneficiary: CORECT OOD/ Municipality of Vratsa
Implementation period: 11/2016 – 03/2017

Design parameters:

  • Demonstration center including 6 pcs modular WWTPs, each with a capacity of 4 PE.

Performed activities:

  • Detailed design of all design parts;
  • Design supervision;
  • Executive documentation;
  • Assistance in start-up, adjustment, and commissioning.

Intention of the Project:
The project aims to establish a center for decentralized wastewater treatment, a combination of modular WWTP working on various technological schemes, respectively requiring different maintenance and service. The center is intended for training and education of different audiences from home and abroad.

The demonstration center also aims to identify the design compliance of the MWWTP with the existing regulatory framework in the field of decentralized wastewater treatment and its implementation.

The overall objective of the training is the development, implementation, and execution of practical training for decentralized treatment of wastewater, in close cooperation with government agencies and ministries.

Investment value of the project: 76 700 € (without VAT)