TECHNICAL DESIGN, DELIVERY, CHIEF-ASSEMBLING, START-UP AND ADJUSTMENT OF WWTP FOR OBJECT: A DOOR MANUFACTURER WITH ADMINISTRATION IN THE LAND OF ELIN PELIN

By 0
379
TECHNICAL DESIGN, DELIVERY, CHIEF-ASSEMBLING, START-UP AND ADJUSTMENT OF WWTP FOR OBJECT: A DOOR MANUFACTURER WITH ADMINISTRATION IN THE LAND OF ELIN PELIN

Employer / Beneficiary: SOLID – 55 OOD
Implementation period: 01/2008 – 10/2008

Design parameters:

  • WWTP for industrial and domestic wastewater from a door manufacturing plant;
  • Parameters of discharged treated water:
    – BOD5 ≤ 25 mg/l;
    – COD ≤ 125 mg/l;
    – Suspended solids ≤ 35 mg/l.

Scope of services:

  • Detailed design;
  • Procedures on issuance of discharge permits;
  • Delivery of basic machine-technological equipment for pumping shaft and MPSOV;
  • Chief-assembling, start-up, and adjustment;
  • Commissioning;
  • Monitoring and control, including sampling and examination of the main parameters of the wastewater at the inlet and outlet of the MWWTP.

Investment value of the project: 27 100 € (without VAT)