Employer/ Beneficiary: Municipality of Hitrino
Implementation period: 06/2010 – 09/2010
Design parameters:
- Modular WWTP for domestic wastewater for village of Zhivkovo with a capacity of 880 PE;
- Modular WWTP for domestic wastewater for village of Trem with a capacity of 660 PE;
- Outlet flow parameters WWTP:
– BOD5 ≤ 25 mg/l;
– COD ≤ 125 mg/l;
– Suspended solids ≤ 35 mg/l;
– TN ≤ 15 mg/l;
– TP ≤ 2 mg/l.
Scope of services:
- Preparation of feasibility studies in two comparable variants;
- Technical and economic analysis;
- Determination of the operating costs and cost of the treated water;
- Selection of an option;
- Preparation of a preliminary design for the selected option under the technological part.
Investment value of the project: 737 300 € (without VAT)