496

Employer/ Beneficiary: S.K.PLOV. EOOD
Implementation period: 11/2008 – 08/2010

Design parameters:

  • WWTP has a capacity of 3,000 PE;
  • Average daily wastewater quantity of 459 m³ / d;
  • Nitrogen and phosphorus removal and discharge into the “sensitive zone”.

Scope of services:

  • Assistance in preparation of technical description of water supply and sewerage systems and technology of drinking and wastewater treatment;
  • Preparation of permit documents for wastewater discharge;
  • Preliminary design for the part of Technology, including:
    – Drinking water treatment plants – for Well 1 – second water horizon about 3 l / s and Well 2 – first water horizon for 5 l / s;
    – Wastewater treatment plants with a capacity of 3000 PE;
    – Water supply and sewerage networks.
  • Preparation of technical design for the gradual construction of WWTP for 3 000 PE in all design parts, coordination and coordination of the project with the institutions and obtaining a permit for construction of WWTP.

Investment value of the project: 87 942 200 € (without VAT)