Employer/ Beneficiary: MUNICIPALITY OF BRATYA DASKALOVI
Implementation period: 08/2008 – 02/2009
Design parameters:
- Modular WWTP with capacity 900 PE – site № 1, average daily wastewater quantity of 125,55 m³/d;
- Modular WWTP with capacity 900 PE – site № 2, average daily wastewater quantity of 125,55 m³/d;
- Modular WWTP with capacity 300 PE – site № 3, average daily wastewater quantity of 46,04 m³/d;
- Outlet flow parameters WWTP:
– BOD5 ≤ 25 mg/l;
– COD ≤ 125 mg/l;
– Suspended solids ≤ 35 mg/l;
– pH = 6,0 – 8,5
– TN ≤ 15 mg/l;
– TP ≤ 2 mg/l.
Scope of services:
- Feasibility studies and preliminary design part technological in two variants for MPSOV.