MODULAR WASTE WATER TREATMENT PLANT FOR VILLAGE OF ORIZOVO, MUNICIPALITY OF DASKALOV BROTHERS, STARA ZAGORA DISTRICT

By 0
390

Employer/ Beneficiary: MUNICIPALITY OF BRATYA DASKALOVI
Implementation period: 08/2008 – 02/2009

Design parameters:

  • Modular WWTP with capacity 900 PE – site № 1, average daily wastewater quantity of 125,55 m³/d;
  • Modular WWTP with capacity 900 PE – site № 2, average daily wastewater quantity of 125,55 m³/d;
  • Modular WWTP with capacity 300 PE – site № 3, average daily wastewater quantity of 46,04 m³/d;
  • Outlet flow parameters WWTP:
    – BOD5 ≤ 25 mg/l;
    – COD ≤ 125 mg/l;
    – Suspended solids ≤ 35 mg/l;
    – pH = 6,0 – 8,5
    – TN ≤ 15 mg/l;
    – TP ≤ 2 mg/l.

Scope of services:

  • Feasibility studies and preliminary design part technological in two variants for MPSOV.