PREPARATION AND IMPLEMENTATION OF INVESTMENT PROJECT FOR CONSTRUCTION OF THE WASTE WATER TREATMENT PLANT AND COMPLETION OF THE SEWERAGE NETWORK FOR THE TOWN OF TUTRAKAN

By 0
295
PREPARATION AND IMPLEMENTATION OF INVESTMENT PROJECT FOR CONSTRUCTION OF THE WASTE WATER TREATMENT PLANT AND COMPLETION OF THE SEWERAGE NETWORK FOR THE TOWN OF TUTRAKAN

Employer/ Beneficiary: Municipality of Tutrakan
Implementation period: 08/2012 – 08/2015

Design parameters:

  • WWTP has capacity of 10 500 PE;
  • Average daily wastewater quantity of Q.= 1 930 m³/d;
  • Nitrogen and phosphorus removal and discharge into Danube River – “sensitive zone”;

Performed activities:

  • Feasibility Study incl. determination populace equivalence and wastewater quality and quantity;
  • Preliminary design of Tutrakan WWTP I all design parts in two options, incl. evaluation of options;
  • BoQ, determination of O&M costs and cost of 1 m³ treated water.

Investment value of the project: 7 363 000 € (without VAT)